When a Respondent wishes to “go” to the Supreme Court and challenge a determination of an Adjudicator for jurisdictional error; that Respondent must also make sure that an application is made to “stay” (“stop”) and restrain the enforcement of the determination of the Adjudicator in the meantime.
A recent reminder of this lesson was provided by the Court of Appeal in the decision of Fitz Jersey Pty Ltd v Atlas Construction Group Pty Ltd [2017] NSWCA 53 (23 March 2017) which resulted in an unfortunate outcome for a Developer whose bank account was garnished for approximately $11m because the Developer did not apply for an order to stay (to stop) the enforcement of an Adjudicators Determination while the Developer challenged that determination in the Supreme Court.
The Developer had engaged a Builder to design and construct a major development in Mascot Sydney.
On 15 November 2016; the Builder served a Payment Claim on the Developer for more than $10.5m plus interest under the Building and Construction Industry Security of Payment Act 1999 (NSW)(SOPA).
On 29 November 2016; the Developer served a Payment Schedule saying that no money was owing.
An Adjudicator determined that the Payment Claim was payable in full.
The Developer did not pay the Adjudicated Amount and on 13 January 2017; commenced proceedings in the Supreme Court challenging the validity of the Adjudication Determination.
The Developer however did not take any steps to stay (stop) the enforcement of the Determination.
Following commencement of the challenge by the Developer; the Builder registered the Determination and on 27 January 2017; obtained a garnishee order directed to the Developer’s Bank which paid the full amount determined by the Adjudicator being $11m to the Builder.
On discovering that the payment of $11m had been made from the Developer’s bank account; the Developer applied to the Supreme Court for urgent orders for the return of the money from the Builder.
The Developer argued that:
The Court was not persuaded by the Developer’s arguments and dismissed the Developer’s application for an injunction.
Justice McDougall who heard the matter said that:
Importantly the Court also noted that there was no evidence before the Court to suggest that the Builder would not be able to repay the $11m.
The Developer appealed the decision of Justice McDougall.
The Court of Appeal dismissed the appeal and found that there was no error in the approach of Justice McDougall.
The Court of Appeal held that:
The proceedings by the Developer to challenge the Adjudicators Determination are continuing (see Fitz Jersey v Atlas Construction Group [2017] NSWSC 340).
The Developer is arguing that the Adjudicator lacked the jurisdiction to make the Determination and that the judgement based on the Determination should be set aside
We will monitor the progress of this case and provide updates in future newsletters.
¨ firstly, there is evidence of a substantial basis of challenge to the determination (on a ground that the courts recognise as being available) and,
¨ secondly, there is reason for thinking that if such a challenge is made and succeeds, the applicant may not enjoy the fruits of its success because the respondent will be unable to repay the adjudicated amount.
¨ Time is of the essence and it will be too late to take steps to restrain and stay the enforcement of a Determination once monies have been paid in accordance with a garnishee order.
¨ For a claimant; the case is a powerful reminder that a garnishee order is an effective way to enforce a Determination of an Adjudicator.
See our recent security of payment articles:
This communication is sent by Kreisson Legal Pty Limited (ACN 113 986 824). This communication has been prepared for the general information of clients and professional associates of Kreisson Legal. You should not rely on the contents. It is not legal advice and should not be regarded as a substitute for legal advice. The contents may contain copyright.
Managing Director
8239 6502 | David.Glinatsis@Kreisson.com.au