27 June 2013
Home Owners Warranty Insurance is a complex area of law that has had numerous amendments over the years. It is important to be aware of the key dates when managing any building with defects to avoid missing critical deadlines.
As from 1 May 1997, New South Wales has the following 2 schemes of insurance:
Since the HBA began on 1 May 1997 there have been 4 significant changes to the private insurance scheme, the latest as recently as 1 April 2009.
In a typical scenario:
For the purpose of defect claim a critical date that needs to be established is that date that the works were completed.
This date is important because:
Establishing when the works were completed until the latest reform was often a difficult exercise.
A failure to properly establish the correct date could mean that the time limit is missed and being time barred from making a claim.
With respect to a contract for residential building work entered into before the recent amendments, section 18E of the HBA states:
18E Proceedings for breach of warranties
1) Proceedings for a breach of a statutory warranty must be commenced within 7 years after:
a) the completion of the work to which it relates, or
b) if the work is not completed:
i) the date for completion of the work specified or determined in accordance with the contract, or
ii) if there is no such date, the date of the contract.
With respect to a contract for residential building work entered into after the recent amendments, section 18E of the HBA states:
18E Proceedings for breach of warranties
1) Proceedings for a breach of a statutory warranty must be commenced in accordance with the following provisions:
a) proceedings must be commenced before the end of the warranty period for the breach,
b) the warranty period is 6 years for a breach that results in a structural defect (as defined in the regulations) or 2 years in any other case,
c) the warranty period starts on completion of the work to which it relates (but this does not prevent proceedings from being commenced before completion of the work),
d) if the work is not completed, the warranty period starts on:
i) the date the contract is terminated, or
ii) if the contract is not terminated-the date on which work under the contract ceased, or
iii) if the contract is not terminated and work under the contract was not commenced-the date of the contract,
e) if the breach of warranty becomes apparent within the last 6 months of the warranty period, proceedings may be commenced within a further 6 months after the end of the warranty period,
f) a breach of warranty “becomes apparent” when any person entitled to the benefit of the warranty first becomes aware (or ought reasonably to have become aware) of the breach.
For the purposes of Section 18E the date of completion is defined in section 3B which states as follows:
3B Date of completion of residential building work
1) The completion of residential building work occurs on the date that the work is complete within the meaning of the contract under which the work was done.
2) If the contract does not provide for when work is complete (or there is no contract), the completion of residential building work occurs on “practical completion” of the work, which is when the work is completed except for any omissions or defects that do not prevent the work from being reasonably capable of being used for its intended purpose.
3) It is to be presumed (unless an earlier date for practical completion can be established) that practical completion of residential building work occurred on the earliest of whichever of the following dates can be established for the work:
a) the date on which the contractor handed over possession of the work to the owner,
b) the date on which the contractor last attended the site to carry out work (other than work to remedy any defect that does not affect practical completion),
c) the date of issue of an occupation certificate under the Environmental Planning and Assessment Act 1979 that authorises commencement of the use or occupation of the work,
d) (in the case of owner-builder work) the date that is 18 months after the issue of the owner-builder permit for the work.
The insurers claim form lists the documents to be lodged.
The main documents consist of the following:
(a) The building contract
(b) Builders certificates of HOW insurance
(c) Value of the building works and details of progress payments
(d) An accurate description of the defective or incomplete works. Unless the list of defects is short the Owners Corporation should obtain a report from a building consultant which sets out:
If an insurance claim is rejected or if an amount approved for payment by the insurer is unsatisfactory, the home owner can appeal to the Consumer Trader and Tenancy Tribunal.
There is a 45 day time limit for appealing a decision of the insurer.
Policies issued | Description | Home Building Regulation 2004 |
Up to 31 August 2005 | Insurance claim is taken to be refused if a decision is not given to claimant within 45 days | Clause 64 |
From 1 September 2007 | Insurance Claim is deemed to be accepted if insurer has not determined liability within 90 days of home owner having provided all necessary claim information | Clause 62A |
Appeals to the CTTT must be lodged within 45 days of written notification by the insurer that the claim has been rejected (clause 65 of the Home Building Regulation 2004).
Managing Director
8239 6502 | David.Glinatsis@Kreisson.com.au