The question of whether a Principal has the right to call on a contractor’s bank guarantee for failure to perform was recently considered in the Court of Appeal of Victoria. Initially, the Supreme Court rejected the entitlement of the Principal to call on bank guarantees based on a strict construction of the contract.
This position was later reversed by the Victorian Court of Appeal.
In June 2007, Lend Lease, the Contractor, and Sugar Australia (“Sugar”), the Principal, entered into a construction contract to upgrade a refined sugar facility at Yarraville in Victoria (“the Contract”).
Under the Contract, Lend Lease, provided two bank guarantees to Sugar as security in the amount of $4,190,000 for its performance.
Sugar alleged that Lend Lease did not comply with its lawful directions, delays and other breaches. As a consequence, Sugar provided Lend Lease with a five-day notice of its intention to call on the two bank guarantees to cover its losses (“the Notice”).
The Contract, which was a modified form of the General Conditions of Contract AS 4910-2002, also contained a clause requiring Sugar to ‘act reasonably’ when seeking recourse to the bank guarantees.
The Contract set out a number of stipulations in relation to how recourse notices were to be issued.
In response to the Notice, Lend Lease suspended works under the Contract claiming that Sugar did not show cause under the Notice and then terminated the Contract.
As a result of Lend Lease’s termination of the Contract, Sugar sought recourse to the bank guarantees.
Lend Lease applied for an interlocutory injunction seeking to restrain Sugar from cashing in the bank guarantees before the alleged breaches had been determined on the evidence after a trial.
Lend Lease claimed that Sugar had not sought recourse to the bank guarantees in compliance with the terms of the Contract, and had not ‘acted reasonably.’ Lend Lease agreed that an interlocutory injunction should be granted to Lend Lease as there was a serious question to be tried.
In response, Sugar claimed that the interlocutory injunction should not be granted, and that, as the issues involved contractual construction in the absence of an assessment of evidence, the court was obliged to finally determine the issue at the interlocutory stage of the proceeding.
As detailed in Cerasola TLS AG v Thiess Pty Ltd & John Holland [2011] QSC 115 (“Cersola”) which cited Clough Engineering Ltd v Oil and Gas Corporation Ltd (2008) 249 CLR 458, where a party seeks to call on a bank guarantee, the Court will generally not step in to prevent the issuer of the bank guarantee from performing its obligation to make payment, unless one of the following recognised exceptions applied:
At first instance, Justice Vickery of the Supreme Court of Victoria:
Sugar appealed to the Victorian Court of Appeal, which allowed the appeal.
Critically, the Victorian Court of Appeal reversed the Supreme Court of Victoria’s decision and discharged the injunction.
The Victorian Court of Appeal reaffirmed Fletcher Construction Australia Ltd v Varnsdorf Pty Ltd (1998) 3 VR 812 (“Fletcher”) which held that bank guarantees:
On that basis, the Victorian Court of Appeal held it would defeat the purpose of bank guarantees if bank guarantees were not payable until determination of the very claims they are designed to secure.
As a consequence of the Court finding that Sugar had a genuine claim under the Contract, Sugar was entitled to call on the bank guarantees without first having to prove its claims against Lend Lease.
This decision, although in Victoria, provides principals with a basis to assert an entitlement to cash in a contractor’s bank guarantee if there is a genuine claim under a construction contract in circumstances where:
The case provides principals with some assurance and practical guidance on when a right to call in a bank guarantee can be exercised.
8239 6500 | excellence@kreisson.com.au