Case note: Arconic Australia Rolled Products Pty Limited v McMahon Services Australia Pty Ltd [2017] NSWSC 1114
Date of decision: 17 August 2017
There have been a number of cases which have made it clear that the Building and Construction Industry Security of Payment Act 1999 (NSW) was not intended to provide another chance for a claimant to issue repeat payment claims and require Adjudicators to determine issues which had already been determined by an earlier adjudicator.
In a recent decision of Arconic Australia Rolled Products Pty Limited v McMahon Services Australia Pty Ltd1 delivered on 17 August 2017; the Supreme Court considered when a repetitious claim under the Act was capable of being determined by an Adjudicator.
The decision contains a helpful review of some key cases and provides clarity as to if and when the Act may permit the determination of a re-agitated Payment Claim.
Arconic engaged McMahon to decommission an aluminium plant.
There were three Payment Claims No 13, 14 and 15 made by McMahon that were the subject of four separate adjudication applications.
The contentious element in each Payment Claim was a claim described in different ways as delay costs for variations relating to undocumented hazardous material discovery.
McMahon made a number of attempts over four adjudication applications to have an issue of a claim for indirect costs determined by an Adjudicator.
The first adjudication application failed because McMahon sought to rely on without prejudice material that was not entitled to put to an Adjudicator.
The second attempt failed because, the Adjudicator concluded that the claim advanced in the second adjudication application was not the same as the claim advanced in the Payment Claim.
The third attempt failed because there was no reference date to support Payment Claim 14 on which the adjudication application was based.
A fourth adjudication application was lodged in respect of Payment Claim 15
The parties agreed that nothing should happen in relation to a fourth adjudication application until the court determined the proceedings.
The amount in each payment claim included an amount, in round figures and exclusive of GST, of $2,344,000 for indirect costs.
Arconic argued that McMahon could not re-agitate that claim in the fourth adjudication application on the grounds that:
McMahon argued that:
The Court reviewed the decision of the Court of Appeal in Dualcorp Pty Ltd v Remo Constructions Pty Ltd2 which said at [69]:
“…for the principle of issue estoppel to apply, the same issue must have been earlier determined as is later sought to be re-agitated“
As also held in Ku-Ring-Gai Council v Ichor Constructions Pty Ltd3, “an issue estoppel can only arise where an issue has already been decided“.
In AE & E Australia Pty Ltd v Stowe Australia4 the Court, at [46], said that the doctrine of issue estoppel applied because, as a matter of substance, the adjudicator had decided the claimant was not entitled to the amounts in question.
The question before the Court turned on the reasons contained in the determination of the second Adjudication Application.
In that determination; the Adjudicator said, that the claim, in the Adjudication Application, was not one that he could consider, because it was materially different to the claim put in the underlying Payment Claim (No 13).
Applying the principles laid out in Leighton v Arogen5 in his determination the Adjudicator said:
[21] Under the Act a claimant cannot advance one basis of entitlement and then change to another and supplement the payment claim with information prepared nominally six (6) weeks after the payment claim was served and claim that the submission is ‘duly made’.
[23] Therefore, with regard to all of the foregoing the adjudicated amount is the scheduled amount that the respondent has agreed to pay of $773,157.43 (inc GST).
According to Justice McDougall, this was not a case where a previous adjudicator had as a matter of substance considered the merits of the question of entitlement and came to a view that there was no entitlement as in the decision of AE & E Australia Pty Ltd v Stowe Australia.
By contrast, His Honour said that this was a case where:
a)the Second Adjudicator took the view that it was not open to him to consider the claim as it had been framed.
b)the Second Adjudicator did not decide the merits of the issue namely whether McMahon was entitled to be paid for the variation claim.
Accordingly; the Court held that McMahon was not prevented by reason of issue estoppel from agitating the fourth adjudication application.
As to the abuse of process issue; the Court made the following observations:
This position is clear from section 13(6) of the Act.
The Court referred to the decision of Stevenson J in Ku-Ring-Gai Council v Ichor Constructions Pty Ltd, where His Honour dealt with the question of abuse of process at [37].
In Ichor, Stevenson J:
The Court held that:
The Act does not preclude the re-agitation of claims.
As confirmed by the authorities however, the Act does preclude the re-agitation of claims if they had been previously determined by an Adjudicator.
The facts of this case were quite unique. Despite a convoluted history; the re agitation of claims in this case was permissible.
The take home message however is that there are still no second chances if a claim is unsuccessful at Adjudication.
It is essential that Claimants prove all the elements of their claim and get the claim right the first time!
This communication is sent by Kreisson Legal Pty Limited (ACN 113 986 824). This communication has been prepared for the general information of clients and professional associates of Kreisson Legal. You should not rely on the contents. It is not legal advice and should not be regarded as a substitute for legal advice. The contents may contain copyright.
1[2017] NSWSC 1114
2(2009) 74 NSWLR 190
3[2014] NSWSC 1534
4[2010] QSC 135
5[2012] NSWSC 1323
Managing Director
8239 6502 | David.Glinatsis@Kreisson.com.au