It is well known that the Building and Construction Industry Security of Payment Act 1999 (the “SOP Act”) makes pay when paid clauses unenforceable. In reality, however, a Claimant may be at risk of recovering an adjudicated amount because a Respondent has not been paid by a Principal.
To address this risk, Division 2A of the SOP Act creates the opportunity for a Claimant subcontractor to require a Principal to withhold the amount of money claimed in a Payment Claim from any money that the Principal owes to the Respondent contractor.
What is perhaps not well understood is how a Claimant can actually access the money that a Principal has withheld under a Payment Withholding Request.
This article sets out the steps that a Claimant must take in order to recover payment from a Principal in the event that a Respondent fails to pay an Adjudicated Amount.
Division 2A of the SOP Act is intended to provide some security to a Claimant in the event that a Respondent defaults on its payment obligations.
Division 2A works as follows:
Although Division 2A of the Act compels a Principal Contractor that has received a Payment Withholding Request to retain money owed to the Respondent to cover the amount of the Payment Claim, nothing in the Division or otherwise in the SOP Act compels the Principal Contractor to actually pay any money to the Claimant.
If a Principal Contractor is required to withhold money but is not compelled to pay the Claimant, what good is that to the Claimant? If the Respondent does not pay the Adjudicated Amount, how can the Claimant access the money that has been withheld by the Principal Contractor?
The answer to these questions is found in s26B (3) (c) of the SOP Act. In order to gain access to any withheld money, the Claimant must issue what is known as a “Notice of Claim” on the Principal. The Notice of Claim is obtained and issued under separate legislation known as the Contractors Debts Act 1997 (the “CD Act”).
The general intent of the CD Act (refer to s5 of the CD Act) is to make it possible for a Subcontractor to obtain payment from a Principal for money owed to the Subcontractor by a Contractor in circumstances where the Contractor is unable or unwilling to pay the Subcontractor. The money is only recoverable by the Subcontractor out of money that is owed or becomes owing by the Principal to the Contractor.
In order to obtain a payment from a Principal under the CD Act, the Subcontractor must:
Therefore, a Claimant under the SOP Act that has issued a Payment Withholding Request on the Principal Contractor must follow the procedures set out in the CD Act and ultimately issue a Notice of Claim on the Principal Contractor in order to recover payment.
Assuming a Payment Withholding Request was issued by a Claimant under the SOP Act, the amount determined to be payable in the Adjudication Determination has gone unpaid by the Respondent and the Claimant then wishes to gain access to money withheld under the Withholding Request, the Claimant will need to take the following steps:
Once the Notice of Claim is served on the Principal Contractor, any money that has been withheld under the Payment Withholding Request (s26A Sop Act) will be required to be paid by the Principal Contractor to the Claimant.
Although the above steps appear straightforward, the processes involved in obtaining each outcome can become complicated.
For example, in order to obtain a Debt Certificate, it is necessary to make an application to the Court by way of Notice of Motion and Affidavit in support. Schedule 10 of the Uniform Civil Procedure Rules 2005 sets out the process that must be followed to apply to the Court to issue a Debt Certificate.
The amounts involved in these types of matters will often mean that Local Courts are required to administer the processes and Registry staff may be unfamiliar with the type of application being made.
As a matter of practicality and in the interests of avoiding delays at the Court, Claimants (or their legal representatives) that intend to enforce the provisions of s26A and 26B of the SOP Act and the related provisions of ss5 to 7 of the CD Act should become familiar with the procedures involved and be able to explain those procedures to court staff if required.
This communication is sent by Kreisson Legal Pty Limited (ACN 113 986 824). This communication has been prepared for the general information of clients and professional associates of Kreisson Legal. You should not rely on the contents. It is not legal advice and should not be regarded as a substitute for legal advice. The contents may contain copyright.