Case note: Mt Lewis Estate Pty Ltd v Metricon Homes Pty Ltd [2017] NSWSC 1121
In the recent decision of Mt Lewis Estate Pty Ltd v Metricon Homes Pty Ltd [2017] NSWSC 1121 delivered on 24 August 2017; the Supreme Court held that a payment claim was invalid because the accompanying supporting statement did not comply with the requirements of section 13(7) and section 13(9) of the Building and Construction Industry Security of Payment Act 1999 (“the Act).
The judgment of the Court provides some helpful guidance on the requirements of a compliant supporting statement under the Act and more particularly how a supporting statement should be completed to ensure that the payment claim is not invalid.
The decision concerned a challenge by a Respondent (St Lewis) to the validity of a determination made by an Adjudicator under the Act in favour of a Claimant (Metricon) on grounds that:
On 16 December 2016 Metricon served a payment claim on Mt Lewis in the sum of $3,316,584 by email with a series of supporting documents, including a supporting statement.
In its Adjudication Response, Mt Lewis argued that the payment claim was not served for the purposes of the Act as it was not accompanied by a compliant supporting statement.
The Adjudicator determined the Payment Claim in favour of Metricon and that St Lewis was responsible to pay the Adjudicators fees in their entirety.
St Lewis commenced proceedings in the Supreme Court to challenge the determination of the Adjudicator.
The declaration in the Supporting Statement was made on 13 December 2016.
The Payment Claim however, was identified as being dated 15 December 2016. The actual date of the Payment Claim was 16 December 2016.
Mt Lewis argued that:
he Court agreed with Mt Lewis.
The Court said:
Although the Court determined that the Payment Claim was invalid due a non compliant supporting statement; the Court still dealt with the second ground and held that the determination was void because it was not made within the time prescribed by section 21(3) of the Act.
But the paperwork does not end with the Supporting Statement.
See our article Personal Liability for false and misleading Statutory Declarations.
It is clear, however, that the Courts are applying pressure on Head Contractors to improve payment behaviour.
This communication is sent by Kreisson Legal Pty Limited (ACN 113 986 824). This communication has been prepared for the general information of clients and professional associates of Kreisson Legal. You should not rely on the contents. It is not legal advice and should not be regarded as a substitute for legal advice. The contents may contain copyright.
Managing Director
8239 6502 | David.Glinatsis@Kreisson.com.au